Errett Road Drainage Work - 2025?
  • Click for original culvert elevations
  • "Downstream" Conditions

    Water from this road drains into the ditch on the east side of Kent Ave. From there, the water travels north along Kent Ave to a culvert under the road between Bayberry and Short Rds, and eventually to the Assawoman Canal.
    DNREC has been working on a plan to improve the drainage along Kent Ave.

    Existing Driveway Culverts
    Several collapsing culverts have been replaced by MBA; one has been temporarily "stented". Additionally, some property owners have paid for culvert replacement/expansions.

    Existing Conditions
    The ditches along Errett are shallower than most of the rest of the community, and need to be lowered (or actually created in the first place) and made wider.

    Upcoming Work
    Not all driveways will be impacted; each is being evaluated individually. MBA met with Lyndon Hitchens on March 18 and discussed the work we'd like done. See the below chart for (not final) details.

    Existing Photos
    The below pictures, starting at the western end, were taken in March 2025. The webmaster is too lazy at the moment to properly code it, so please right-click on any photo to see a larger version... Additional basic notes have been entered for each driveway, and more certainly will be added. Such as, oh, say, elevations...



    Left (west) side of driveway Driveway Right (east) side of driveway Address/Owner/Misc Notes
    1-Gruenspecht
    OK-swale put into buried pipe January 2012
    3-Tyson
    OK-swale put into buried pipe January 2012
    5-Laigle
    OK; culvert replaced 2014 or so
    7-Robinson
    culvert replaced 2014 or so; gravel needed on driveway portion on MBA property
    rip-rap needs adjustment; culvert opening is partially obstructed
    9-Quinlan
    overhanging branches to be removed
    driveway OK
    11W-Glasgow
    driveway culvert OK; some swale work
    11E-Glasgow
    driveway culvert OK; swale reengineering from here eastward
    13W-Barila
    replace concrete culvert sections w/ new 10" pipe
    landscaping timbers?
    13E-Barila
    replace steel pipe w/ new 10" pipe
    landscaping timbers?
    15-Bolasky
    replace concrete culvert sections w/ new 10"
    new swale to be dug
    17-Weninger
    replace steel pipe w/ new 10" pipe
    swale to be widened/deepened
    19W-Chodnicki
    replace concrete sections w/ new 8" pipe
    19E-Chodnicki
    replace concrete sections w/ new 8" pipe
    21W-Paul
    culvert replaced Jan 2021; probably needs to be lower; new 8" pipe
    21E-Paul
    culvert replaced Jan 2021; probably needs to be lower; new 8" pipe
    23-Whitmore
    replace concrete sections w/ new 8" pipe; dig swale
    25-Ighemat

    new house; driveway same location?
    replace steel pipe w/ new 8"
    27-Sokolowski
    reengineer swale
    leave driveway culvert pipe in place if elevations work out



    Right (east) side of driveway Driveway Left (west) side of driveway Address/Owner/Misc Notes
    2-Lyons
    OK
    4-Burgess/Mounteer
    Collapsed steel culvert replaced January 2012
    6-Lewis
    OK; swale re-engineering starts just east of this driveway
    8W-Paul
    Replace with new 10"; swale widened/deepened
    8E-Paul
    Replaced June 2024; swale work needed; 9 (mostly small) trees between swale and street to be removed
    10-Chappell
    Keep if elev OK
    12-Mintz
    Replace w/ new 10" pipe; 1 tree to be removed
    14W-Throop/Parish
    Replace concrete sections w/ new 10" pipe; 3 trees to be removed
    14E-Throop/Parish
    Replace stented steel pipe w/ new 10" pipe
    16W-Kaufman/Friedman
    Replace w/ new 8" (try not to touch permeable pavers adjacent road)
    remove trees growing on top of culvert
    16E-Kaufman/Friedman
    Replace w/ new 8" (try not to touch permeable pavers adjacent road)
    18-LePage
    Keep if elevation works (pavers on top of concrete pipe sections; concrete walls adjacent driveway)
    20W-Matthews
    Replaced June 2024
    20E-Matthews
    Replaced June 2024
    22-Neaton/Renwick
    No work (hold off until work on adjacent Beach Plum has been evaluated)
    22-Neaton/Renwick
    No work (hold off until work on adjacent Beach Plum has been evaluated)
    24-Murphy
    No work (hold off until work on adjacent Beach Plum has been evaluated)

    This Page: http://middlesexbeach.org/cfc/drainage/errett.htm.
    Last update: 3/19/25.